Timco

Beginning with a pre-engineered building, overhead crane runways were installed along with 2 cranes and partition wall / liner panels. Two towers (50’) were erected with 45’ hoist beams along with a new
mezzanine structure with stairs and railing.

  • Erected pre-engineered building
  • Installed 2 overhead crane runways
  • Set 2 overhead cranes
  • Constructed partition walls and liner panel
  • Erected (2) 50’ towers with 45’ hoist beams
  • Erected mezzanine w/stairs and railing